Author MS Project 2003
Mark

2003-12-03, 8:24 am

I cannot outdent a subtask even though I have no group
filter selected and I am showing all the relevant show
summary tasks in the tools menu

As a ms Project trainer I am finding it frustrating as
I've never encountered this in previous versions
The only thing I could do was to delete the phase and
start again - which is ridiculous
Please help!

Mark
chabdesign

2004-04-01, 12:24 am


Dear Mark,
I had the same problem. Don't we look like fouls in front of a class
full of adults...

Anyway, because I can to you comment first and other may do the
same...
Goto the MS Project 2003 WEB page. there seems to be a fix offered by
Micros...
Good luck


Mark wrote:
> *I cannot outdent a subtask even though I have no group
> filter selected and I am showing all the relevant show
> summary tasks in the tools menu
>
> As a ms Project trainer I am finding it frustrating as
> I've never encountered this in previous versions
> The only thing I could do was to delete the phase and
> start again - which is ridiculous
> Please help!
>
> Mark *




--
chabdesign
------------------------------------------------------------------------
Posted via http://www.mcse.ms
------------------------------------------------------------------------
View this thread: http://www.mcse.ms/message139143.html